Building a power plant in Georgia takes four main approvals: an environmental decision or screening decision, a construction permit, a grid connection agreement and, for plants above 15 MW, a generation licence from the regulator. This guide explains who issues each one, which projects need a full environmental impact assessment (EIA), the legal timelines and how to work with communities so that a permitted project actually gets built. Rules are as of October 2026.

Which permits does a power plant need in Georgia?

ApprovalIssued byWho needs it
Environmental decision (after EIA) or screening decisionEnvironmental agency under the Environmental Assessment Code (source)Hydropower from 2 MW, wind farms, thermal plants from 2 MW (see below)
Construction permitThe municipality or the Ministry of Economy and Sustainable Development, depending on the facility's classEvery new plant
Grid connection agreementGSE for the transmission grid, the distribution company for lower voltagesEvery grid-connected plant
Generation licenceGNERC, the energy regulator (source)Plants above 15 MW
Land rightsPublic Registry (ownership or lease); state land by lease or purchaseEvery plant
Revenue support (optional)Ministry of Economy renewable auctions (source)Projects seeking a price guarantee

The order matters: under the Code, a licence or permit that depends on an environmental decision can only take effect after that decision is issued (source).

Does my project need an EIA?

The Environmental Assessment Code sorts projects into two annexes (source):

ProjectAnnexWhat happens
Hydropower plant of 5 MW or moreAnnex IFull EIA is mandatory
Hydropower plant of 2–5 MWAnnex IIScreening decides whether an EIA is needed
Wind farm (any size)Annex IIScreening
Combustion power plant of 2 MW or moreAnnex IIScreening
Hydropower under 2 MWNot listedNo EIA under the Code; other rules still apply
Solar PV plantNot named in the annexesConfirm early with the environmental agency, especially for large ground-mounted plants

EIA applications, scoping reports and public hearings are published on the National Environmental Agency's portal (source).

How long does the EIA take?

The Code sets fixed windows for each stage (source):

StageLegal timeline
Scoping: public discussion10–15 days after the application is published
Scoping opinion (list of required studies)26–30 days after the application is registered
Baseline studies and EIA reportSet by the developer; hydrology, fish and biodiversity work usually needs at least a full year of data
Public comments on the EIA reportWithin 40 days of publication
Public hearing of the EIA report25–30 days after publication
Environmental decision85–90 days after the application is registered

The decision has no expiry date, but it becomes invalid if the activity does not start within 7 years, and it can be transferred to a new owner through an accelerated 10-day procedure (source). Both points matter when you buy a development-stage project.

Construction permit

A construction permit is required for every plant, and the authority depends on the facility's class and location: large energy facilities are usually permitted at national level by the Ministry of Economy and Sustainable Development, smaller ones by the municipality. Permits are typically staged (site use conditions, architectural design, then the permit itself), and the environmental decision has to be in place first.

Power Plant Permits in Georgia: EIA, Licences, Grid Connection and Stakeholders (2026)

Grid connection

Grid capacity is now one of the tightest constraints. GSE, the transmission system operator, has set limits on how much new variable renewable capacity the grid can take: 0.75 GW for wind and 0.5 GW for solar, according to Galt & Taggart's June 2025 market review (source). In practice:

  • Apply for connection early and treat the connection offer as a key project document.
  • Check who pays for substation and line upgrades and when the reinforcements are scheduled.
  • For hydro, check whether the connection allows full output in the spring flood, when lines are most loaded.

Generation licence

Under the Law on Energy and Water Supply, plants up to 15 MW do not need a generation licence but must notify the regulator; larger plants need a GNERC licence, and microgeneration (100 kW in the law, raised by GNERC to 500 kW) follows net metering or net billing rules; see our net metering guide (source). See our guide to GNERC and its role.

Stakeholders: the approvals that are not on paper

A complete permit file does not guarantee a project. The Namakhvani hydropower project in western Georgia faced more than 200 days of protests, and in September 2021 the Turkish developer ENKA terminated its agreement with the government (source). The lesson for investors is that community acceptance is a real permitting risk.

StakeholderWhy they matter
Local residents and landownersLand access, construction disruption, water use, compensation
Municipality and local councilLocal permits, roads, public hearing logistics
Environmental NGOsBiodiversity, river flows and cumulative impacts; active at hearings and in court
Ministries and agenciesEnvironmental decision, construction permit, land, support schemes
Lenders (EBRD, ADB, IFC and others)International standards that often go beyond Georgian law

What works:

  1. Engage before the scoping hearing, not at it, and explain the project in Georgian with clear maps.
  2. Agree how environmental flows, fish passage and water use for irrigation will be handled.
  3. Hire locally, and put commitments in writing with a public grievance mechanism.
  4. Publish monitoring results during construction and operation.

Permit checklist when buying a project

  • Environmental decision: issued, its conditions, started within 7 years, transferable to the buyer.
  • Construction permit: which stage is complete, and whether the design still matches the permit.
  • Grid connection agreement: capacity, voltage, upgrade costs and deadlines.
  • Generation licence or regulator notification, depending on size.
  • Land title and leases registered in the Public Registry, including access roads and the line route.
  • Records of public hearings, community commitments and open grievances.

Our regulatory and ESG advisory teams review permit files and community risk for investors.

Planning or buying a power project in Georgia? Contact us.